Sections

Weather Forecast

Close
Advertisement
The entrance to the Commons on the west side is buttoned up for the winter months.

WDC construction progressing

Email Sign up for Breaking News Alerts
news Wadena, 56482
Wadena PJ
(218) 631-1621 customer support
Wadena Minnesota 314 S. Jefferson, P.O. Box 31 56482

Here's an update on the construction at Wadena-Deer Creek secondary school:

• Pouring cement for locker room floors this week; pouring the academic wing the week of Dec. 12.

Advertisement
Advertisement

• Exterior brick has started on the north end of the academic wing.

• Roof parapets and roofing is ongoing over the academic wing. A parapet is a low wall projecting vertically from the edge of the roof.

• Steel-stud framing started on the second-floor classrooms.

• All underground plumbing is completed.

• Both underground and overhead electrical conduit is being installed.

• The building will be temporary enclosed this week; about 33 percent of the building is now being heated to 50 degrees.

• Special inspections are ongoing; WDC has passed all current inspections.

Visit www.wdc2155.k12.mn.us for updates.

Advertisement
news@wadenapj.com
Advertisement
Advertisement
randomness