Preliminary construction schedule for Maslowski Wellness and Research Center released

Email News Alerts

By Lori Schloeder Gress

Advertisement

Below is the preliminary construction schedule for the Maslowski Wellness and Research Center:

Construction Phase:

Site Preparation                                                               10/07/13 to 11/15/13      30 days

Building Excavation and Foundations                      11/18/13 to 12/27/13      30 days