Below is the preliminary construction schedule for the Maslowski Wellness and Research Center:

Construction Phase:

Site Preparation                                                               10/07/13 to 11/15/13      30 days

Building Excavation and Foundations                      11/18/13 to 12/27/13      30 days

Building Structure                                                            12/30/13 to 05/02/14      90 days

Exterior Enclosure                                                           05/05/14 to 06/13/14      30 days

Interior Construction                                                      06/16/14 to 10/03/14      80 days

Site Work and Landscaping                                          05/12/14 to 08/01/14      60 days

Substantial Completion                                                 10/13/14 to 10/13/14        0 days

Final Cleaning and Systems Commissioning          10/06/14 to 11/14/14      30 days

Final Completion                                                              11/14/14 to 11/14/14        0 days