Photo by Dana Pavek/WDC Schools The block walls are going up on the east side of the locker rooms this week at the Wadena-Deer Creek School construction site. The steel is being installed around and above the administrative office area; the building storm and sanitary underground is being installed at both the gymnasium and kitchen area; the underground electrical system has started at the main electrical room; and 188 of the 200 geothermal wells have been drilled.

Construction update